Engineering & consulting · Energy, industry, infrastructure
Quality, inspection and completion for industrial projects
We support owners, contractors and manufacturers in energy, industry and infrastructure: quality surveillance, equipment inspection and testing, mechanical completion, audits, project and contract management, training.
| No. | Activity | Reference | Contr. | Client | TPI |
|---|---|---|---|---|---|
| 1.1 | Material receipt, 3.1 certificates | EN 10204, project spec. | P | R | R |
| 2.1 | Welding procedures and welder qualification | ASME IX | P | H | W |
| 3.1 | Visual inspection of welds | ASME B31.3 §341 | P | S | W |
| 3.2 | Radiographic / ultrasonic testing | ASME V, ISO 17636 / 17640 | P | R | R |
| 4.1 | Hydrostatic test (1.5 × design pressure) | ASME B31.3 §345 | P | H | W |
| 5.1 | Final quality dossier | Project spec. | P | R | R |
Clients
- ETAP
- Streicher
- Hydrokarst Groupe
- Tragedel
- SODEPS
- SERI Engineering
- Smart Control
- SNIFT
What we do
Services
Each assignment has a written scope, named deliverables and a fixed price.
Quality support and expertise
Owner’s quality representative, review and approval of contractor quality plans and inspection and test plans, quality surveillance, NCR and KPI follow-up, QA/QC staff secondment.
Equipment inspection and acceptance
On the buyer’s behalf (second party): vendor assessment, manufacturing surveillance, factory acceptance test (FAT) witnessing, final and pre-shipment inspection with release note, expediting, site receiving and SAT.
Mechanical completion and commissioning support
Systemisation, punch-list management, verification of mechanical completion dossiers, commissioning supervision, handover dossiers, taking-over and warranty support.
Audits
Supplier and subcontractor (second-party) audits, project quality audits, internal audits on your behalf, ISO 9001:2026 gap assessment, ISO 9001 implementation support.
Project and contract management
Owner’s project management support, project controls (schedule, cost, earned value, risk), procurement support for buyers, contract administration under FIDIC conditions, claims and dispute avoidance.
Training
In-company training
ISO 9001:2026 internal auditor; quality on construction projects; mechanical completion, commissioning and taking-over; industrial and EPC project management; Tunisian public procurement; construction contracts based on FIDIC conditions (independent course); production planning and scheduling; Lean and problem solving. Delivered in French or English.
Independence. Reindaxia does not issue certificates or perform statutory inspections; these belong to accredited or approved bodies. We disclose any conflict of interest before an assignment and never work for two parties on the same project.
Latest insights
Field experience on quality, completion and FIDIC contracts.
Tests on completion, taking over and the defects period: FIDIC Clauses 9 to 11 seen by a quality engineer
Read the article →Notices and claims under FIDIC Clause 20: keeping a register and meeting the 28 and 84 day limits
Read the article →Quality under FIDIC Sub-Clause 4.9: quality plan, inspection and test plans, and proof of compliance
Read the article →Tell us about your need